Wind farm sites
Click here for interactive map
(posted with kind permission of Caru Teifi)
Proposed wind farm developments in Brecon and Radnor
click images for details
Aberedw
108 MW 18 turbines 200m tip height located 4km SE of Buith Wells
Bryn Gilwern
84 MW 16 turbines 220m tip height located 4km E of Llandrindod Wells
Nant Mithil
205 MW 31 turbines up to 220m tip height located 3km NW of New Radnor
Other proposed wind farm developments in the Heart of Wales
-
Promoter: Bute Energy
Location: NW of Llangurig
Capacity: 46 MW - 7 turbines 200m tall
Timeline:
Sept/Oct 2022: Initial consultation with local communities, stakeholders and specialist consultees
2022 - 2023: Current phase, evolution of our proposals - informed by consultation feedback
Spring 2024: Statutory consultation with local communities, stakeholders and specialist consultees
Summer 2024: Submission for an application for a DNS
Summer 2025: Welsh Ministers expected to determine application
2025: Procurement of turbines, construction contracts, and associated electrical and civil engineering work
-
Promoter: Galileo
Location: 10 km South of Tregaron
Capacity: 175 MW - 25 turbines 230m tall
Timeline:
December 2023 Announced
-
Promoter: Bute Energy
Location: SE of Machynlleth
Capacity: 171 MW - 26 turbines 220m tall
Timeline:
January 2024: Current phase - project launch EIA scoping
January/March 2024: Initial consultation
Late 2024/Early 2025: Statutory consultation
Late 2025: Submission of DNS application
-
Promoter: EDF Renewables
Location: S of Newtown
Capacity: 85 MW 17 turbines 150m tall
Timeline:
Jan 2020: announced
2020-2023: informal consultations EIA scoping etc
2023: next stage of planning announced
2024 DNS application to be submitted
-
Promoter: Bute Energy
Location: S of Tregaron
Capacity: 260 MW - 40 turbines 220m tall
Timeline:
January 2024: Current phase - project launch
Summer/autumn 2024: Initial consultation and EIA scoping
Early 2025: DNS notification
Mid 2025: Statutory consultation
Late 2025: Submission of DNS application
-
Promoter: Bute Energy
Location: SW of Llanderfyl
Capacity: 165 MW - 25 turbines 200m tall
Timeline:
Current phase evaluating and considering feedback
Spring 2024 meteorological mast installation
Summer 2024 statutory consultation
Autumn 2024 submission of DNS application
-
Promoter: Bute Energy
Location: SE of Llangurig
Capacity: 99 MW - 15 turbines 200m tall
Timeline:
Sept/Oct 2022: Initial consultation with local communities, stakeholders and specialist consultees
2022 - 2023: Current phase, evolution of our proposals - informed by consultation feedback
Spring 2024: Statutory consultation with local communities, stakeholders and specialist consultees
Summer 2024: Submission for an application for a DNS
Summer 2025: Welsh Ministers expected to determine application
2025: Procurement of turbines, construction contracts, and associated electrical and civil engineering work
2028: Construction and first export of clean green energy to the National Grid
-
Promoter: Belltown Power
Locataion: NE of Lampeter
Capacity 25.2 MW- 6 turbines 230m tall
Timeline:
June 2023: first consultation events
Sept 2023 - Feb 2024: preparation of planning submission
Jan 2024 - Feb 2024: second consultation events
March 2024: Target planning submission
Jan 2024 - Feb 2024: second consultation events
March 2024: Target planning submission
-
Bute Energy - Blaencothi Energy Park (E of Lampeter, N of Llandovery)
Bute Energy - Garreg Fawr Energy Park (N of Sennybridge)
Wind 2 - Banc y Celyn (S of Builth Wells)