Aberedw

Aberedw

Promoter: Bute Energy

Details: capacity 108MW 18 Turbines 3 km East of Builth Wells

Timeline:

Winter 2023: current phase. Non-statutory consultation with communities, stakeholders and consultees 6 weeks

Winter 2023 - autumn 2024: Evaluating and considering feedback received to progress the project design 

Summer 2024: Meteorological Mast Installation (nb, this assumes planning permission, not mentioned.)  

Throughout 2024: Design development, EIA and reporting 

Winter 2024: Statutory pre-application consultation with communities, stakeholders and consultees

Early 2025: Submission of DNS application 

Comments: Set in pastoral countryside overlooking Builth Wells and the river Wye